Prachi Mahajan

I have 7 Years of experience in UI/UX Designer. My specialty is in Adobe Photoshop, Adobe Illustrator, Coral Draw, Wireframing, Prototyping, Figma, Adobe XD, Branding and creating attractive Responsive Website and Web Application using HTML5, CSS3.

Services

What We Offer

GRAPHIC DESIGN

UI Design
Website & Digital Design
Brading & Visual Identity
Iconography
Typography

ILLUSTRATION

Motion Graphics
Animation
Visual Effects

WIREFRAMING TOOLS

Figma
Sketch
Adobe XD
Balsamiq
Axure

FRONT END DEVELOPMENT

HTML5 / CSS3
JS & Jquery
Bootstrap

Welcome to your next website!

Portfolio

Web and Graphic Design Work





Update IFC RFI Page(EPM3.0 Web Application)



Update IFC RFI Page WireFraming(In Adobe XD)


UX Case Study-Request For Information management(RFI) page.

1)Problem Statement:
Request For Information management(RFI) page.

2)User Experience Research:
Time of RFI creation.
Number of Days taken for response to RFI.
RFI processing & Management.
Effectiveness of RFI tracking with regards to importance.
I studied about managing RFI's for your construction projects,construction management, The anatomy of a Request for Infomtaion(RFI),
RFI role in construction process,construction engineering and management,Project Management Procedures-Request for Information,
Impact & control of RFI's on construction projects,Early contractor involvment schedule performance.
Establishment of RFI process and hierarchy which informs the contractor how RFIs are to be submitted.
Unique tracking number of each RFI.
Importance of the RFI determined by the contractor.
Date when the owner,architect or engineer should respond to the RFI by.
Possible solution to the issue or problem.
Estimate of impact of the RFI on cost and schedule.
Use of electronic RFI tracking and monitoring system including RFI log.

3)Primary Search:
1)How can the RFI management /tracking process be improved in construction projects?
2)How effective the suggested items/policies for RFI management are?
3)How effective RFI creation in terms of number of dyas for response?
4)How effective is RFI tracking with regards to important?

4)Proto Personas:
Suggested solution is require
Photo/related drawing or specification number
Expected impacts on costs and duration
RFIs were tracked and discussed in weekly meetings with the owner and architect.